ROSEMERRYN: STAGE 22
January 2025: The civil works are ahead of programme and are currently tracking to be completed in April. This would mean that titles could be issued in July. Once all the services (power, fibre, and streetlights) are completed we will provide a further update as these works have the potential to delay the expected completion date.